Update - September 25, 2025
Construction continues at Shingle Spit as crews are making good progress. Due to the tide schedule and timing for pouring and curing of four tranches of precast concrete deck tiles, the updated launch date is expected for mid-November. Some night work may be required due to tides, however the majority of the remaining work will be completed during daytime hours.
An exact completion date is unknown at this time. Please check back into this project page for updated dates, construction photos, and timelines.
Update - August 7, 2025
Construction has begun for the much anticipated new Shingle Spit Boat Launch. Demolition will begin this week (August 7 onwards) with installation of the new pilings beginning the following week and into late August. The project is expected to be completed by mid-September, barring any delays or weather impacts.
Image
![]() |
Image
![]() |
Please note: keep clear of the construction area and allow contractor crews to complete their work uninterrupted. For more information and updates, keep visiting this project page.
Shingle Spit Boat Launch Proposed Design
Background
In 2018, the Comox Valley Regional District (CVRD) received a Licence of Occupation with the Province to manage and upgrade the boat launch at Shingle Spit. An inspection in 2018 by an engineering firm determined that the boat launch was in an advanced state of disrepair and should be replaced. Since 2018, the CVRD has tried unsuccessfully to find funding through grants to replace the boat launch. The Shingle Spit Boat Launch is the only boat launch on Hornby Island and provides an important amenity for recreational boaters and for emergency evacuation.
In 2023, funding was secured to design and construct a new launch at Shingle Spit. In 2024, the CVRD is focused on design, permitting and community engagement. Early discussions and meetings with an ad hoc Boat Launch Committee on Hornby have helped develop the design below. Construction for the boat launch is scheduled to take place in August 2025, with dates to be determined.
CVRD Parks staff and Cascara Engineering hosted an open house on May 22, 2024 to provide updates on the Shingle Spit Boat Launch design and seeking feedback from the community.